:: Reuters ::
 
 
• Location:
11 Upper Grosvenor Street, London W1
• Project Manager:
Reuters Facilities Managers
• Quantity Surveyor:
Appleyard & Trew
• Form of Contract:
Cityspace Management Contract
• Project Area: 6,000 sq ft
• Project Value:
£230,000
• Contract Period:
8 weeks
• Project Details:

Refurbishment of Georgian townhouse, with adaptations for office use

• Scope of Works:

CAT B fit out
- Demolition and Strip Out
- Plastering
- Tea points
- Decoration including repair to Fibrous
  plasterwork
- Fitment of broadloom carpets
- Upgrade of Mechanical Systems
- New Electrical Systems
- Joinery
- Comms Room and installation of
  new riser
- Furniture selection and co-ordination
- Replacement of lighting fitments and
  switches
- IT & telecoms installation